|
This
is David pulling in cables 24 at a time. As you can see the boxes are stacked
up in 3 rows of 8 at the end of the runs and pulled back towards the area
where the racks will be positioned. Once the main run has been laid the
cables are split into bundles of 6 and fed out to each floor box
in that area. |
| Here we have nearly 600
cables ready to terminate into the racks. The patch panels are 1u x 24
way so by pulling them in 24 at a time makes it easier to organize them
ready for dressing into the racks. |
|
|
This shows the area where
the racks will be sited and you can see we have already started to put
the bundles of 24 cables into 'socks'. Using socks makes it easier and
quicker to dress the cables in but they also make it harder to add or replace
cables. |
| This is another picture
of the area where the racks will be positioned and it shows the main cable
run leading up to the racks. At this point the cables are in 48's which
then get split back to their 24's just before the racks. |
|
|
Here is a close up of the
back of the racks showing the cables dressed up the sides and the sock
trimmed to length. |
| This is the back of the
racks. |
|
|
And here is the front of
the racks ready to be enclosed in their own room and have the hubs installed. |
| This is the main comms room
on the ground floor where all of the backbone cables terminate, it also
houses the telephone switch and server racks. Some of the patching has
been done. |
|
|
Here we see the same room
with patching nearly completed. It is important to realize just how many
patch cables will be required on an installation and make adequate provision
for managing them. |
| This is part of a finished
floor, it is the same sort of area that the picture of David was taken
(top of the page) but on the floor below. Its hard to believe that this
was such a mess only two weeks before. |
|
|
This is a different Dave
and a different comms room! |
| Here are two Krone panels
which have been prepared ready for terminating. |
|
|
Part terminated panel. |
| This picture shows the easy
way to lay the pairs into the IDC blocks without over twisting or untwisting
the pairs too much. |
|
|
The punch down tool should
be kept at 90 degrees to the connection, this avoids splaying the IDC blades.
(As the wire is pushed into the block the blades either side cut into the
insulation and make contact with the core). |